CLIENT : Lend Lease

Project objective
The project comprised 448 apartments and 18 townhouses on a 2.5ha site, with a third of the project open space.
RCI Infrastructure involvement
Supply and install 1.2 kms of stormwater, including pits to Glen Eira Council requirements. Connect to existing 7 meters deep 100 year old Melbourne Water pit. Methodology included cross stitching the final connection to enable the integrity of the Melbourne Water pit to remain.
Project completion
Stormwater works delivered on time and on budget.